Research and Academic publication
Keyword: Year: Month: Date:

28-12-2015 - Stations are Gradually to be Exposed along with Progress of LRT Taipa Line
28-12-2015 - Footbridge of LRT Stations are Being Gradually Constructed
26-10-2015 - Gradually Making Room for Lane Space along with Progress of the LRT Construction
26-10-2015 - LRT Viaduct is constructed in the Green Belt to Enhance Traffic Flow
31-07-2015 - Journal Article:“Connected Mobility: On Track and Online when on the Move” by Tdhrail “The Asian Railway Magazine 2015”
31-07-2015 - Journal Article: Evolution and Future of Metro Technology by Tdhrail “The Asian Railway Magazine 2015”
31-07-2015 - Journal Article:“Trends in Railway asset management from the Operator and the Suppliers’ perspectives” by Tdhrail “The Asian Railway Magazine 2015”
29-12-2014 - The Introduction of Trussed Hoisting of Bridge Deck to Accelerate Light Rapid Transit Construction
29-12-2014 - The Wide Application of Box Girder Structure for Light Rapid Transit Viaducts in Rapid Transit Construction
25-08-2014 - LRT Northern Section Introduction - LRT Projects are monitored by independent environmental units
14-08-2014 - LRT Northern Section Introduction ─ Mature Driverless LRT System
12-08-2014 - LRT Northern Section Introduction ─ Comparison of Mass Transit Systems
30-06-2014 - Introduction of environmental assessment to build environment-friendly good-quality LRT system
30-06-2014 - Multiple supervisions to implement the environmentally friendly construction in LRT project
14-04-2014 - The advantageous prestressed LRT viaducts achieve harmonious synergy with the surrounding environment
14-04-2014 - Multiple tests are conducted on 100-Year Concrete of LRT Viaduct to guarantee durability
10-02-2014 - LRT viaduct adopts precast construction method to increase efficiency and reduce environmental impact
10-02-2014 - LRT construction is given greater flexibility in the use of lifting precast parts
14-10-2013 - Zero-emission LRT trains save energy and provide green travel environment
14-10-2013 - Green and simple LRT stations to match with the environment
1 | 2 | 3 |
->

2018.03-Installation of embedded E&M conduits at staircase wall in Basement 1 2018.03-Pouring concrete for top structural slab at Northern Ramp 2018.03-Formwork installation of staircase wall in Basement 1 2018.03-Application for waterproofing membrane at ventilation shaft in Northern Ramp 2018.03- Diaphragm wall construction works is in progress 2018.03- Excavation works of the trench of diaphragm wall 2018.03- The construction unit is inspecting the power rail installation at the depot stabling yard 2018.03- The power rail installation inside depot 2018.03- The guide rail installation on the viaduct at Taipa Ferry Terminal Station 2018.03-The guide rail installation on the viaduct at Airport Station 2018.03- The construction on the viaduct at Airport Station 2018.03- The guide rail installation 2018.03- The construction unit is installing guide rail on the viaduct at Avenida do Aeroporto 2018.03- Power rail installation at Avenida do Aeroporto 2018.03-Guide rail installation at Avenida da Nave Desportiva 2018.03- The construction inside the Cotai East Station 2018.03- System equipment installation at Avenida da Nave Desportiva 2018.03- Construction inside the Lotus Checkpoint Station 2018.03- Electric cables installation inside Lotus Checkpoint Station 2018.03- Equipment installation in Cotai West Station engine room 2018.03- The construction unit is installing signal cables on the viaduct at Avenida Cidade Nova 2018.03- System equipment installation at Estrada da Baía de Nossa Senhora de Esperança 2018.03- The construction unit is installing signal cables on the viaduct at Estrada da Baía de NossaSenhora de Esperança 2018.03- The train performs signal system testing along Avenida do Estádio 2018.04-The train moving towards Avenida do Estádio 2018.03- Platform doors installation in Stadium Station is completed 2018.03- Access control gates installation in Stadium Station has started 2018.03- The construction of the power rail at Avenida do Estádio is completed 2018.03- Construction on viaduct at Estrada Governador Albano de Oliveira 2018.03- Platform doors installation in Jockey Club Station is completed 2018.03-The construction unit is inspecting noise barriers on the viaduct at Rua dos Jogos da Ásia Oriental 2018.04- The train moves on the viaduct at Avenida dos Jogos da Ásia Oriental 2018.03-The installation of the system equipment at Avenida dos Jogos da Ásia Oriental is basically completed 2018.03- The train is driven into Ocean Station 2018.03-The construction unit is installing illumination system inside Ocean Station 2018.03- The construction unit is inspecting the operation of the system 2018.03- The construction unit is testing the operation of the train and the related equipment. 2018.03- The construction unit is inspecting the gap between the train and the viaduct 2018.03- The train is driven out from Ocean Station 2018.03- The train is driven into Jockey Club Station 2018.03- Construction units are inspecting the operation conditions of the signal system 2018.03-The first phase of LRT dynamic test has been launched for the Taipa Line.