Shipment of LRT Carriages Begins Today
Published on
20-10-2017

The first batch of the Light Rail Transit train carriages started being shipped to Macao officially from Japan today (20th). It is expected that the carriages will be delivered to the LRT “Ocean Station” in early November. Subsequently, various works on systematic tests will be commenced to coordinate with the objective to open the Taipa Line to traffic in 2019.

The LRT Taipa Line entered the stage of systems and equipment installations at the beginning of this year. Some railway sections are in the conditions where commissioning works of the trains, systems and equipment can be commenced. Upon coordination, Mitsubishi Heavy Industries will arrange for the shipment of LRT train carriages in batches to Macao. In particular, in the first batch, 4 train carriages in total, accompanied with the special reparation vehicles, already started being shipped from Japan officially today (20th). It is expected that the train carriages will arrive in Macao at the end of this month; upon the completion of the customs clearance procedure, it is foreseen that the carriages can be transported to the LRT “Ocean Station”, located in Avenida dos Jogos da asia Oriental, Taipa, for the commencement of various works on testing.

Each LRT train carriage is 11.8 meters in length, 2.8 meters in width, 3.8 meters in height, and 15 tons in weight. Having considered that it is necessary to pass by the main roads of the city centre in the course of transportation, the construction team started simulated transportation the other day to ensure the safety and smoothness in the process of official delivery. 



2018.03-Installation of embedded E&M conduits at staircase wall in Basement 1 2018.03-Pouring concrete for top structural slab at Northern Ramp 2018.03-Formwork installation of staircase wall in Basement 1 2018.03-Application for waterproofing membrane at ventilation shaft in Northern Ramp 2018.03- Diaphragm wall construction works is in progress 2018.03- Excavation works of the trench of diaphragm wall 2018.03- The construction unit is inspecting the power rail installation at the depot stabling yard 2018.03- The power rail installation inside depot 2018.03- The guide rail installation on the viaduct at Taipa Ferry Terminal Station 2018.03-The guide rail installation on the viaduct at Airport Station 2018.03- The construction on the viaduct at Airport Station 2018.03- The guide rail installation 2018.03- The construction unit is installing guide rail on the viaduct at Avenida do Aeroporto 2018.03- Power rail installation at Avenida do Aeroporto 2018.03-Guide rail installation at Avenida da Nave Desportiva 2018.03- The construction inside the Cotai East Station 2018.03- System equipment installation at Avenida da Nave Desportiva 2018.03- Construction inside the Lotus Checkpoint Station 2018.03- Electric cables installation inside Lotus Checkpoint Station 2018.03- Equipment installation in Cotai West Station engine room 2018.03- The construction unit is installing signal cables on the viaduct at Avenida Cidade Nova 2018.03- System equipment installation at Estrada da Baía de Nossa Senhora de Esperança 2018.03- The construction unit is installing signal cables on the viaduct at Estrada da Baía de NossaSenhora de Esperança 2018.03- The train performs signal system testing along Avenida do Estádio 2018.04-The train moving towards Avenida do Estádio 2018.03- Platform doors installation in Stadium Station is completed 2018.03- Access control gates installation in Stadium Station has started 2018.03- The construction of the power rail at Avenida do Estádio is completed 2018.03- Construction on viaduct at Estrada Governador Albano de Oliveira 2018.03- Platform doors installation in Jockey Club Station is completed 2018.03-The construction unit is inspecting noise barriers on the viaduct at Rua dos Jogos da Ásia Oriental 2018.04- The train moves on the viaduct at Avenida dos Jogos da Ásia Oriental 2018.03-The installation of the system equipment at Avenida dos Jogos da Ásia Oriental is basically completed 2018.03- The train is driven into Ocean Station 2018.03-The construction unit is installing illumination system inside Ocean Station 2018.03- The construction unit is inspecting the operation of the system 2018.03- The construction unit is testing the operation of the train and the related equipment. 2018.03- The construction unit is inspecting the gap between the train and the viaduct 2018.03- The train is driven out from Ocean Station 2018.03- The train is driven into Jockey Club Station 2018.03- Construction units are inspecting the operation conditions of the signal system 2018.03-The first phase of LRT dynamic test has been launched for the Taipa Line.