News  
The First Batch of LRT Train Carriages Arrive at Macao
Published on
27-10-2017

The first batch of the LRT train carriages arrived at Macao today (29th). Upon the completion of a series of customs clearance procedure, it is expected that they can be transported to the “Ocean Station” by next week the soonest.

In the first batch, 4 LRT train carriages and 2 special reparation vehicles in total have been started being delivered from Japan in earlier days. After the maritime transportation which lasted more than a week, the carriages arrived at the Ka Ho Deepwater Pier, Coloane in the morning today (29th), and the respective customs declaration procedure commenced subsequently. Later, arrangements will be made to transport them to the LRT “Ocean Station” near Avenida dos Jogos da Asia Oriental, Taipa consecutively to start various works on tests.

In particular, the lifting works of 2 special reparation vehicles are expected to commence this Saturday (4th), while the transportation of the remaining 4 train carriages can be arranged next week the soonest. At that time, temporary traffic limitation will be implemented at the side of Avenida dos Jogos da Asia Oriental, Taipa which is close to Ocean Garden. Drivers should be reminded. 



2018.03-Installation of embedded E&M conduits at staircase wall in Basement 1 2018.03-Pouring concrete for top structural slab at Northern Ramp 2018.03-Formwork installation of staircase wall in Basement 1 2018.03-Application for waterproofing membrane at ventilation shaft in Northern Ramp 2018.03- Diaphragm wall construction works is in progress 2018.03- Excavation works of the trench of diaphragm wall 2018.03- The construction unit is inspecting the power rail installation at the depot stabling yard 2018.03- The power rail installation inside depot 2018.03- The guide rail installation on the viaduct at Taipa Ferry Terminal Station 2018.03-The guide rail installation on the viaduct at Airport Station 2018.03- The construction on the viaduct at Airport Station 2018.03- The guide rail installation 2018.03- The construction unit is installing guide rail on the viaduct at Avenida do Aeroporto 2018.03- Power rail installation at Avenida do Aeroporto 2018.03-Guide rail installation at Avenida da Nave Desportiva 2018.03- The construction inside the Cotai East Station 2018.03- System equipment installation at Avenida da Nave Desportiva 2018.03- Construction inside the Lotus Checkpoint Station 2018.03- Electric cables installation inside Lotus Checkpoint Station 2018.03- Equipment installation in Cotai West Station engine room 2018.03- The construction unit is installing signal cables on the viaduct at Avenida Cidade Nova 2018.03- System equipment installation at Estrada da Baía de Nossa Senhora de Esperança 2018.03- The construction unit is installing signal cables on the viaduct at Estrada da Baía de NossaSenhora de Esperança 2018.03- The train performs signal system testing along Avenida do Estádio 2018.04-The train moving towards Avenida do Estádio 2018.03- Platform doors installation in Stadium Station is completed 2018.03- Access control gates installation in Stadium Station has started 2018.03- The construction of the power rail at Avenida do Estádio is completed 2018.03- Construction on viaduct at Estrada Governador Albano de Oliveira 2018.03- Platform doors installation in Jockey Club Station is completed 2018.03-The construction unit is inspecting noise barriers on the viaduct at Rua dos Jogos da Ásia Oriental 2018.04- The train moves on the viaduct at Avenida dos Jogos da Ásia Oriental 2018.03-The installation of the system equipment at Avenida dos Jogos da Ásia Oriental is basically completed 2018.03- The train is driven into Ocean Station 2018.03-The construction unit is installing illumination system inside Ocean Station 2018.03- The construction unit is inspecting the operation of the system 2018.03- The construction unit is testing the operation of the train and the related equipment. 2018.03- The construction unit is inspecting the gap between the train and the viaduct 2018.03- The train is driven out from Ocean Station 2018.03- The train is driven into Jockey Club Station 2018.03- Construction units are inspecting the operation conditions of the signal system 2018.03-The first phase of LRT dynamic test has been launched for the Taipa Line.